Atkinson was awarded the contract for underground development and mining operations at the Golden Sunlight Mine in Whitehall, Montana in an to attempt to retrieve 36,000 ounces of gold that was estimated to remain at the bottom of an existing pit mine.
  
Atkinson’s work included 1,300 feet of 14-foot-wide-by-14-foot-high, sub-level access and miscellaneous access ramp at a -15 to +15 percent grade, 1,500 feet of 13-foot-wide by 13-foot-high sub-levels at a +2 percent grade, ground support including friction bolts, and 12-foot dywidags and mesh, 120 feet of 8-foot-by-8-foot man-way, secondary escape and ventilation raise, 10,000 feet of reverse circulation definition drilling, and approximately 260,000 tons of long-hole stop production.